J U D G M E N T
On the 9th of June 2010 Plaintiffs herein commenced the instant acting against the Defendants.
By an amended writ of summons filed on 31st May 2013, the Plaintiffs claimed the following reliefs against the Defendants:
a. An order directed at the 1st and 2nd Defendants jointly and severally to pay the amount of GH44,550 which Plaintiff paid and /or deposited to 1st Defendant’s account for the supply of 45 tons of Iron rods
b. Interest on the said amount at the prevailing bank rate from April 2010 till date of final payment
c. Cost including counsel’s cost
Plaintiffs allege that they are a limited liability company registered under the laws of Ghana and engaged in retailing of cement, iron rods and other building materials whilst 1st Defendant is a limited liability company registered under the laws of Ghana and engaged in manufacturing of iron rods. That 2nd Defendant is an employee of the 1st Defendant.
Plaintiffs allege further that sometime in 2009 officers of…