The Plaintiff’s claims against the Defendants were as follows:
The recovery of the sum of GH¢543, 499.92 being the amount outstanding as at October 31st 2013 on the credit line facility advanced to the 1st Defendant.
The recovery of the sum of GH¢124,718.80 being the amount outstanding as at October 31st 2013 on the medium term loan facility advanced to the 1st Defendant.
Interest on the sum of GH¢543, 499.92 at the agreed rate of 30.25% from October 31st 2013 to the date of final payment
Interest on the sum of GH¢124,718.80 at the agreed rate of 31% from October 31st 2013 to the date of final payment.
The recovery of the sum of GH¢185,991.45 being the amount outstanding as at October 31st 2013 as penal charges on the two facilities.
Penal interest on the sums outstanding on the two facilities at the agreed rate of 12% to the date of final payment.
An order for the judicial sale of the parcel of land located at Ablekuma Accra that is stamped as LVD8607A/2011.
An order for the sale of the stoc…