CITY ENGINEERING NIGERIA LTD. V. FEDERAL HOUSING AUTHORITY
(1997) JELR 45475 (SC)
Supreme Court
•
SC.204/1992
•
17 Jul 1997
•
Nigeria
Coram
MUHAMMADU LAWAL UWAIS JSC;
SALIHU MODIBBO ALFA BELGORE JSC;
ABUBAKAR BASHIR WALI JSC;
IDRIS LEGBO KUTIGI JSC;
MICHAEL EKUNDAYO OGUNDARE JSC;
EMMANUEL OBIOMA OGWUEGBU JSC;
SYLVESTER UMARU ONU JSC;
Appearances
S. Sowemimo For Appellant
Respondent unrepresented For Respondent
Judgement
<p><strong>M. E. OGUNDARE, J.S.C: </strong> The principal question that calls for determination in this appeal is: When does the statutory period of limitation start to run for the purpose of the enforcement of an arbitration award; is it at the date of the accrual of the original cause to action or is it at the date of the arbitral award?</p><p> The parties herein entered into a written agreement dated 17th day of December, 1974 whereby the appellant was to build a number of housing units at Festac Town, Badagry Road, Lagos. The agreement contained in its Clause 30 a provision to submit all matters in dispute in connection with the execution of the contract to arbitration. Sub-clause (4) of clause 30 provided that the award of the arbitrator would be final and binding. A dispute arose between the parties in the course of the execution of the contract. The respondent rather than settle the dispute inter partes by its letter dated 5th December, 1980 threatened to terminate the co…</p>