JUDGMENTÂ
In a writ filed on 26th July, 2016, Plaintiff sought the following reliefs:Â
a. A declaration that plaintiff was constructively dismissed by the defendant and same was unlawful and wrongful.Â
b. An order against the Defendant to pay the Plaintiff his severance award in accordance with practice at the Defendant Company.Â
c. Damages for breach of contract.Â
d. An order compelling the Defendant to return Plaintiff’s service vehicle. e. Costs including legal fees.
Plaintiff was Defendant’s employee initially stationed at Tarkwa. Plaintiff’s employment was for an indefinite period. By letter dated 14th October, 2015 (exhibit B), Plaintiff was transferred to Tema to begin work by 1st November, 2015. Plaintiff was to let Defendant know what reasonable assistance he needed to help with moving any of his personal effects. It is Plaintiff’s case that he shuttled between Tema and Tarkwa in the performance of his duties. He averred further that, appropriate office was not provided h…